Xcel Warns Grid May Need Coal Plants Longer Amid Delays In New Energy Projects
By: Mark Jaffe | The Colorado Sun
The plants in Pueblo and Hayden were slated to phase out between 2025 and 2030. Now the company has proposed running all their units for four more years.
Xcel Energy, facing what it says is a shortfall in electricity generating capacity for the next two years, is proposing to run its four coal-fired units until 2030.
Comanche Unit 2, in Pueblo, was supposed to close at the end of 2025. One unit at the Hayden Station is to close in 2027 and the second unit is slated to shut in 2028. Comanche Unit 3 is set to close in 2030.
Comanche 3 suffered turbine damage in August taking the unit offline. Xcel Energy initially said repairs would be completed in June, but in a March 2 report to state regulators the company said it h...