Cost of Colorado dam project doubles to $2.7 billion as towns fear the price
By Michael Booth | The Colorado Sun
Northern Water has halted multiple contract bids while it scales back designs to hold together a coalition of water agencies
Northern Water has halted some design and construction contracts and is cutting back its multibillion-dollar, two-dam supply project after its biggest customer said it was pulling out, officials said, as they detailed how the budget for their decades-long ambition suddenly jumped to $2.69 billion from $2 billion.
Four design-and-build contracts for the Northern Integrated Supply Project, meant to serve growth in 15 communities and water agencies, were pulled from the bidding process for at least three to four months while engineers consider how costs could be cut, Northern Water General Manager Brad Wind said in...